Overdue project milestone evidence workbook
Key facts
This guide is not legal advice and laws/rules may change; consult a qualified professional for personalized assistance. Use at your own risk.
For an overdue project invoice, trace each billed line back to the agreed milestone and the buyer’s acceptance record. Allocate deposits and credits to the lines they cover. Send disputed variations to the project owner with the exact evidence they need to resolve.
Worked example
A studio issued INV-412 for €18,000 under work order WO-412. A buyer sign-off dated 2 October covers €12,000 for M1. The other €6,000 is a scope variation the buyer says was outside the signed work order. The parties’ deposit record allocates €5,000 to M1 and finance has posted a €1,000 credit against M1.
| Billed item | Acceptance record | Amount and allocation | Next action and owner |
|---|---|---|---|
| M1 · base implementation | WO-412 §2, deliverable log DL-7 and buyer acceptance AC-9 covering the billed work. | €12,000 less €5,000 allocated deposit less €1,000 posted credit = €6,000 open. | Finance keeps the acceptance, invoice receipt and deposit allocation together. Confirm the agreed terms and the buyer’s current payment response. |
| V2 · scope variation | Change request CR-6 and delivery log exist. Buyer disputes authority to approve the variation. Signed acceptance is missing. | €6,000 invoiced, no deposit allocated. €6,000 remains in dispute review. | Project lead obtains the buyer’s written position and approval record. Finance lists this balance separately before choosing the next step. |
Check the balance against the statement
€18,000 billed less €5,000 allocated and €1,000 credited leaves €12,000 open. The worksheet flags €6,000 with acceptance evidence and €6,000 that needs dispute review. That split is an evidence assessment. Verify the ledger against the contract and the latest buyer correspondence before acting.
What to attach
Use the signed order and applicable change requests, acceptance or remediation records, invoice and AP receipt, payments and credits, and the active dispute correspondence. Record who approved each milestone and when. If acceptance depends on a term you cannot verify, write down the missing evidence and assign an owner.
Copy the worksheet
| Invoice | Milestone or variation | Contract reference | Acceptance document and date | Currency | Billed amount | Deposit applied | Posted credit | Open amount | Disputed amount | Evidence gap | Next owner and date |
|---|
If a documented, eligible B2B amount remains overdue after you check the project record, Start a collection case.