Overdue project milestone evidence workbook

Tie each billed milestone to acceptance evidence, allocate deposits and isolate disputed variations in a copyable project invoice ledger.
Upload a case

Key facts

For an overdue project invoice, trace each billed line back to the agreed milestone and the buyer’s acceptance record. Allocate deposits and credits to the lines they cover. Send disputed variations to the project owner with the exact evidence they need to resolve.

Worked example

A studio issued INV-412 for €18,000 under work order WO-412. A buyer sign-off dated 2 October covers €12,000 for M1. The other €6,000 is a scope variation the buyer says was outside the signed work order. The parties’ deposit record allocates €5,000 to M1 and finance has posted a €1,000 credit against M1.

Illustrative workflow
Billed itemAcceptance recordAmount and allocationNext action and owner
M1 · base implementationWO-412 §2, deliverable log DL-7 and buyer acceptance AC-9 covering the billed work.€12,000 less €5,000 allocated deposit less €1,000 posted credit = €6,000 open.Finance keeps the acceptance, invoice receipt and deposit allocation together. Confirm the agreed terms and the buyer’s current payment response.
V2 · scope variationChange request CR-6 and delivery log exist. Buyer disputes authority to approve the variation. Signed acceptance is missing.€6,000 invoiced, no deposit allocated. €6,000 remains in dispute review.Project lead obtains the buyer’s written position and approval record. Finance lists this balance separately before choosing the next step.

Check the balance against the statement

€18,000 billed less €5,000 allocated and €1,000 credited leaves €12,000 open. The worksheet flags €6,000 with acceptance evidence and €6,000 that needs dispute review. That split is an evidence assessment. Verify the ledger against the contract and the latest buyer correspondence before acting.

What to attach

Use the signed order and applicable change requests, acceptance or remediation records, invoice and AP receipt, payments and credits, and the active dispute correspondence. Record who approved each milestone and when. If acceptance depends on a term you cannot verify, write down the missing evidence and assign an owner.

Copy the worksheet

InvoiceMilestone or variationContract referenceAcceptance document and dateCurrencyBilled amountDeposit appliedPosted creditOpen amountDisputed amountEvidence gapNext owner and date

If a documented, eligible B2B amount remains overdue after you check the project record, Start a collection case.

References

Small Business Commissioner invoicing guidance

Illustration of a free e-book representing the 'Free International Debt Collection Guide.' This guide offers proven debt collection techniques. Get your free copy now.
FREE GUIDE

Download our free debt collection guide

Practical steps to get unpaid invoices paid, at home and abroad. Download our debt collection guide for free.

Thank you! The guide will land in your inbox shortly
Oops! Something went wrong while submitting the form.