Milestone payment terms
Key facts
Track two dates for each milestone. Record the event that lets you invoice and the start date for counting payment days. For example, written acceptance can trigger invoicing while confirmed receipt of that invoice starts the 30-day payment term.
This guide is not legal advice and laws/rules may change; consult a qualified professional for personalized assistance. Use at your own risk.
Set a billable event for each part of the project
Write down the deliverable, who can accept it, what shows it meets the agreed criteria, and the invoice amount. Include the purchase order reference and the address or portal for submitting invoices. A target delivery date belongs in the project schedule. The agreed billing event is what finance needs before raising the invoice.
Decide how the buyer will report rejected or incomplete work. Keep the earlier submission, the buyer’s response and the later acceptance together. If one deliverable is disputed, check the agreement and the records for each other milestone before changing its invoice or due date.
Three milestones on a EUR 30,000 project
Fictional example. A supplier and a buyer agree that written acceptance by the buyer’s project lead makes each milestone billable. Payment is due 30 calendar days after the buyer’s accounts payable portal confirms invoice receipt.
- Design sign-off, EUR 6,000. The project lead signs off on 3 November 2026. The portal confirms invoice receipt on 4 November. Payment is due on 4 December.
- Accepted pilot, EUR 12,000. The buyer rejects the first submission on 9 December because a listed acceptance test fails. After a correction, the lead accepts the pilot on 15 December. The portal confirms invoice receipt on 16 December. Payment is due on 15 January 2027.
- Accepted rollout, EUR 12,000. Rollout has a target delivery date, with acceptance still pending. The supplier forecasts the amount and leaves the invoice due date open until the agreed receipt event occurs.
Give finance the records it will need
For each line in the schedule, keep the deliverable ID, agreed acceptance criteria, accepted version, approver, acceptance record, invoice number, receipt confirmation, due date, and allocated payments or credits. When payment is late, check which trigger occurred and calculate the remaining balance from those records before sending a reminder.
See how to reconcile invoice wording and due dates or how advance deposits work. For more options, use the payment terms guide. If an undisputed cross-border business invoice for accepted work remains overdue, you can start a collection case with Debitura.
See Boeing’s example of milestone billing conditions and the UK Cabinet Office’s model contract guidance on milestone testing and payment.