Net 30 vs Net 60 payment terms

Net 30 gives a buyer 30 days to pay the full invoice from the agreed start date. Net 60 gives 60. For a supplier deciding whether to grant the extra month, check how much remains unpaid at the same time, what it costs to carry that balance and which bills come due before the customer pays.
Create your free account

Key facts

Start with the open balance. If you invoice USD 40,000 every 30 days and the buyer pays on time, moving from Net 30 to Net 60 can leave a second USD 40,000 invoice open throughout the billing cycle. Compare that extra exposure with your credit limit before you agree.

Put both deadlines on the same calendar

Suppose your agreement starts the clock on the invoice date and counts calendar days. For an invoice issued on 5 October 2026, Net 30 is due on 4 November and Net 60 is due on 4 December. If the agreement starts on confirmed receipt or another event, use that event and write the actual due date on the invoice.

In this example, the supplier owes USD 25,000 for materials on 20 November. On-time Net 30 payment arrives before that bill is due. On-time Net 60 payment arrives after it. List the cash you have available on 20 November before deciding whether you can carry the longer term.

Estimate the added balance and cost

Take a supplier that issues a USD 40,000 invoice to the same buyer every 30 days. If the buyer pays every invoice on its due date, payments and new invoices are recorded on the same day, and there are no disputes or credits, the open balance after those postings settles around USD 40,000 on Net 30 and USD 80,000 on Net 60. Payments received after the next invoice is issued can temporarily push exposure higher.

If the supplier borrows the entire extra USD 40,000 at an illustrative 12% annual simple rate, 30 days cost about USD 395. The calculation is USD 40,000 × 0.12 × 30 ÷ 365, before any fees. If the additional balance is financed continuously for a full year at that rate, the annual cost is USD 4,800. Use your own funding cost, billing schedule and actual payment dates. Model a late payment separately.

With a USD 60,000 limit for this buyer, the proposed USD 80,000 open balance exceeds the limit by USD 20,000 even if payments are punctual. The funding cost and the credit limit answer different questions. An affordable funding cost still leaves the limit breach to resolve.

Decide what you can offer the buyer

  1. List the supplier bills, wages and other cash outflows due before the buyer’s proposed payment date.
  2. Project the largest unpaid balance for that buyer, including any orders you plan to release before the next payment. Compare it with the approved credit limit.
  3. If the projected balance is too high, limit new orders until payment clears or ask for a deposit. A shorter term such as Net 45 can reduce how long the balance stays open, but it can still leave two invoices open at once on a 30-day billing cycle. Recheck both the peak balance and the cash gap before agreeing to new terms.
  4. Record the start event and the actual due date in the order, invoice and ledger. Review actual payment dates before extending the same terms to later orders.

See how Net 60 due dates work, compare Net 45 invoice terms, or use the invoice wording and due-date reconciliation examples. The payment terms guide covers other options. If a cross-border business invoice is already overdue, you can start a collection case with Debitura.

References: J.P. Morgan’s working-capital guide and Stripe’s net payment terms guide.