Net 75 payment terms
Key facts
Check before agreeing: in business-to-business contracts covered by the EU Late Payment Directive, a term longer than 60 days must be expressly agreed and must not be grossly unfair to the creditor. National rules can be stricter.
This guide is not legal advice and laws/rules may change; consult a qualified professional for personalized assistance. Use at your own risk.
How to calculate a net 75 due date
Start from the trigger the terms name and add 75 calendar days. Counting across month ends is where errors happen, so let your invoicing system calculate the date and print it on the invoice.
| Invoice date | Days counted | Net 75 due date |
|---|---|---|
| 15 January 2027 | 16 in January, 28 in February, 31 in March | 31 March 2027 |
Cross-border example
A Spanish furniture maker supplies a German retail chain and invoices EUR 42,000 on 15 January 2027. The buyer asks for net 75. Because both companies are in the EU, the maker checks that the longer term is written expressly into the supply contract and that it can carry the receivable until 31 March 2027. German law, in section 271a of the Civil Code, follows the same 60-day rule as the directive. Some countries go further: France, for example, caps most B2B payment periods at 60 days from the invoice date, or 45 days end of month if the contract expressly says so, so check the buyer’s country before signing. If the buyer later pays late, the agreed date is the reference point for interest and recovery costs.
Use the payment terms by country table to see the maximum B2B terms in each market before you accept a long term.
Before you agree net 75
- Set a credit limit that covers 75 days of sales to this buyer, not just one invoice.
- Write the term expressly into the contract, with the trigger and calendar-day count.
- Ask whether an early payment discount or a shorter term such as net 60 would work for both sides.
See the payment terms guide. If a cross-border business invoice remains overdue, you can open Debitura case intake.
Reference: EU Late Payment Directive 2011/7/EU, Article 3.