Retainage: what it is and how to get it released

Retainage, called retention in the UK, is the part of each progress payment that the paying party holds back until the work is finished. It gives the owner or main contractor security that defects will be fixed. For the contractor or subcontractor, it is money already earned but not yet paid, so it needs its own tracking and its own invoice when release is due.
Create your free account

Key facts

Retainage in one line: each progress payment is paid minus an agreed percentage, often up to 10%, and the retained total is paid when the contract’s release conditions are met. On US federal construction contracts, FAR 32.103 allows retainage only where progress is unsatisfactory and limits it to 10% of the approved estimated amount.

How retainage is calculated

Multiply each approved progress billing by the agreed retainage rate. Pay the rest now and record the withheld amount as retainage receivable on the contractor’s side.

Progress billingApproved amountRetainage at 10%Paid nowRetained to date
1USD 100,000USD 10,000USD 90,000USD 10,000
2USD 120,000USD 12,000USD 108,000USD 22,000
3USD 100,000USD 10,000USD 90,000USD 32,000
4USD 80,000USD 8,000USD 72,000USD 40,000

On this USD 400,000 subcontract, USD 40,000 is still owed when the last progress payment arrives. Some contracts reduce the rate once the job is half complete, so check the clause rather than assuming a flat percentage.

When retainage is released

The contract sets the trigger. Common triggers are substantial or practical completion, final acceptance, the end of a defects period, or receipt of documents such as lien waivers and as-built drawings. In the UK, retention is often released in two parts, one at practical completion and the rest at the end of the defects period, but the contract decides.

On US federal contracts, FAR 32.103 says retained amounts are to be paid promptly once all contract requirements are complete. Many US states also have prompt payment rules for retainage, especially on public projects, so check the law where the project is located.

Example: chasing a retainage release across borders

A Canadian glazing subcontractor finished its USD 400,000 package on a US office project in March 2027, with USD 40,000 retained. The subcontract releases retainage 30 days after final acceptance of the subcontractor’s work and receipt of a final lien waiver. Final acceptance is recorded on 12 April 2027 and the waiver is sent the same day, so release falls due on 12 May 2027. The subcontractor sends a separate release invoice on 12 April with the acceptance record and waiver attached, and diarises a follow-up for 13 May.

Keep retainage from going missing

  • Track retainage per contract as a separate receivable, with its release trigger and due date.
  • Collect the documents the release needs before the trigger date.
  • Invoice the release separately and follow up as you would any overdue invoice.

See also pay when paid vs pay if paid and the payment terms guide. If a cross-border business invoice remains overdue, you can open Debitura case intake.