Retainage: what it is and how to get it released
Key facts
Retainage in one line: each progress payment is paid minus an agreed percentage, often up to 10%, and the retained total is paid when the contract’s release conditions are met. On US federal construction contracts, FAR 32.103 allows retainage only where progress is unsatisfactory and limits it to 10% of the approved estimated amount.
This guide is not legal advice and laws/rules may change; consult a qualified professional for personalized assistance. Use at your own risk.
How retainage is calculated
Multiply each approved progress billing by the agreed retainage rate. Pay the rest now and record the withheld amount as retainage receivable on the contractor’s side.
| Progress billing | Approved amount | Retainage at 10% | Paid now | Retained to date |
|---|---|---|---|---|
| 1 | USD 100,000 | USD 10,000 | USD 90,000 | USD 10,000 |
| 2 | USD 120,000 | USD 12,000 | USD 108,000 | USD 22,000 |
| 3 | USD 100,000 | USD 10,000 | USD 90,000 | USD 32,000 |
| 4 | USD 80,000 | USD 8,000 | USD 72,000 | USD 40,000 |
On this USD 400,000 subcontract, USD 40,000 is still owed when the last progress payment arrives. Some contracts reduce the rate once the job is half complete, so check the clause rather than assuming a flat percentage.
When retainage is released
The contract sets the trigger. Common triggers are substantial or practical completion, final acceptance, the end of a defects period, or receipt of documents such as lien waivers and as-built drawings. In the UK, retention is often released in two parts, one at practical completion and the rest at the end of the defects period, but the contract decides.
On US federal contracts, FAR 32.103 says retained amounts are to be paid promptly once all contract requirements are complete. Many US states also have prompt payment rules for retainage, especially on public projects, so check the law where the project is located.
Example: chasing a retainage release across borders
A Canadian glazing subcontractor finished its USD 400,000 package on a US office project in March 2027, with USD 40,000 retained. The subcontract releases retainage 30 days after final acceptance of the subcontractor’s work and receipt of a final lien waiver. Final acceptance is recorded on 12 April 2027 and the waiver is sent the same day, so release falls due on 12 May 2027. The subcontractor sends a separate release invoice on 12 April with the acceptance record and waiver attached, and diarises a follow-up for 13 May.
Keep retainage from going missing
- Track retainage per contract as a separate receivable, with its release trigger and due date.
- Collect the documents the release needs before the trigger date.
- Invoice the release separately and follow up as you would any overdue invoice.
See also pay when paid vs pay if paid and the payment terms guide. If a cross-border business invoice remains overdue, you can open Debitura case intake.